docs(state): record phase 14.1 context session

This commit is contained in:
curo1305
2026-06-26 19:23:24 +02:00
parent 20a31bf6f4
commit 0d56a5b486
+28 -24
View File
@@ -2,33 +2,33 @@
gsd_state_version: 1.0
milestone: v0.3
milestone_name: Reimagining Cloud Storage integration
current_phase: 14
current_phase_name: selective-analysis-and-byte-cache
status: in_progress
stopped_at: Phase 14 Plan 09 complete
last_updated: "2026-06-23T18:11:05.105Z"
last_activity: 2026-06-23
last_activity_desc: Phase 14 Plan 06 byte cache for open/preview/download complete
current_phase: 14.1
current_phase_name: cloud-local-file-parity-hardening
status: not_planned
stopped_at: Phase 14.1 context gathered
last_updated: "2026-06-26T17:23:14.358Z"
last_activity: 2026-06-26
last_activity_desc: Inserted Phase 14.1 cloud/local parity hardening and Phase 14.2 cross-codebase review and cleanup
progress:
total_phases: 6
total_phases: 8
completed_phases: 4
total_plans: 30
completed_plans: 30
percent: 67
percent: 50
---
# Project State
**Project:** DocuVault
**Status:** Phase 14 in progress — Plan 14-06 complete
**Last Updated:** 2026-06-23
**Status:** Phase 14.1 pending planning — Cloud/Local File Parity Hardening
**Last Updated:** 2026-06-26
## Current Position
Phase: 14 (selective-analysis-and-byte-cache) — IN PROGRESS
Plan: 9 of 9
Status: Plans 14-01 through 14-06 complete. Next: execute 14-07
Last activity: 2026-06-23Phase 14 Plan 06 byte cache for open/preview/download complete
Phase: 14.1 (cloud-local-file-parity-hardening) — NOT PLANNED
Plan: 0 of 0
Status: Phase 14 complete. Next: plan inserted Phase 14.1.
Last activity: 2026-06-26Inserted Phase 14.1 cloud/local parity hardening and Phase 14.2 cross-codebase review and cleanup
## Phase Status
@@ -37,7 +37,9 @@ Last activity: 2026-06-23 — Phase 14 Plan 06 byte cache for open/preview/downl
| 12. Cloud Resource Foundation | CONN-04, CLOUD-01, CLOUD-08, CACHE-01, CACHE-02, SYNC-01 | **Complete** |
| 12.1 Fix Nextcloud Root Listing and Sync Visibility | CONN-04, CLOUD-01, CACHE-01, SYNC-01 | **Complete** |
| 13. Virtual-Local Cloud Operations | CONN-01..03, CLOUD-02..07, CLOUD-09 | **Complete** |
| 14. Selective Analysis and Byte Cache | ANALYZE-01..07, CACHE-03..05 | **Planned** |
| 14. Selective Analysis and Byte Cache | ANALYZE-01..07, CACHE-03..05 | **Complete** |
| 14.1 Cloud/Local File Parity Hardening | CLOUD-02, ANALYZE-01..07, CACHE-03..05 | **Not started** |
| 14.2 Cross-Codebase Review and Cleanup | Cross-cutting quality gates | **Not started** |
| 15. Unified Smart Search | SEARCH-01..07 | **Not started** |
| 16. Change Tracking and Reliability | SYNC-02..04 | **Not started** |
@@ -45,9 +47,9 @@ Last activity: 2026-06-23 — Phase 14 Plan 06 byte cache for open/preview/downl
| Metric | Value |
|---|---|
| Phases complete | 3 / 6 |
| Requirements satisfied | 17 / 36 |
| Plans complete | 21 / 21 |
| Phases complete | 4 / 8 |
| Requirements satisfied | 30 / 36 |
| Plans complete | 30 / 30 |
| Tests at milestone start | 277 |
| Phase 12.1 P01 | 823s | 4 tasks | 14 files |
| Phase 12.1 P02 | 2100s | 3 tasks | 13 files |
@@ -100,7 +102,9 @@ Last activity: 2026-06-23 — Phase 14 Plan 06 byte cache for open/preview/downl
- v0.2 completed: UI overhaul, admin panel rearchitecture, responsive layout, codebase quality (2026-06-17)
- v0.2 archived to `.planning/milestones/v0.2-ROADMAP.md`
- v0.3 in progress: Phase 12 (cloud resource foundation) complete 2026-06-21; Phase 12.1 (Nextcloud fix) complete; Phase 13 (virtual-local cloud operations) complete 2026-06-23 — v0.3.0 shipped
- Phase 14 (selective analysis and byte cache) planned 2026-06-23
- Phase 14 (selective analysis and byte cache) complete 2026-06-23 — v0.4.0 shipped
- Phase 14.1 inserted after Phase 14: Cloud/Local File Parity Hardening (URGENT)
- Phase 14.2 inserted after Phase 14: Cross-Codebase Review and Cleanup (URGENT)
### Open Questions
@@ -112,16 +116,16 @@ None.
## Session Continuity
**Stopped at:** Phase 14 Plan 09 complete
**Stopped at:** Phase 14.1 context gathered
_Updated at each phase transition._
| Field | Value |
|---|---|
| Last session | 2026-06-23T18:11:05.100Z |
| Next action | Execute 14-07 |
| Last session | 2026-06-26T17:23:14.347Z |
| Next action | Plan 14.1 |
| Pending decisions | None |
| Resume file | .planning/phases/14-selective-analysis-and-byte-cache/14-08-PLAN.md |
| Resume file | .planning/phases/14.1-cloud-local-file-parity-hardening/14.1-CONTEXT.md |
## Decisions