docs: start milestone v0.3 Reimagining Cloud Storage integration
This commit is contained in:
+17
-16
@@ -1,29 +1,30 @@
|
||||
---
|
||||
gsd_state_version: 1.0
|
||||
milestone: v0.2
|
||||
milestone_name: UI Overhaul and Optimization
|
||||
current_phase: 11
|
||||
status: complete
|
||||
last_updated: "2026-06-17"
|
||||
last_activity: 2026-06-17 -- v0.2 milestone archived
|
||||
milestone: v0.3
|
||||
milestone_name: Reimagining Cloud Storage integration
|
||||
status: planning
|
||||
last_updated: "2026-06-17T21:15:24.719Z"
|
||||
last_activity: 2026-06-17
|
||||
progress:
|
||||
total_phases: 4
|
||||
completed_phases: 4
|
||||
total_plans: 33
|
||||
completed_plans: 33
|
||||
percent: 100
|
||||
total_phases: 0
|
||||
completed_phases: 0
|
||||
total_plans: 0
|
||||
completed_plans: 0
|
||||
percent: 0
|
||||
---
|
||||
|
||||
# Project State
|
||||
|
||||
**Project:** DocuVault
|
||||
**Status:** v0.2 milestone complete — ready for next milestone
|
||||
**Status:** v0.3 milestone planning — defining requirements
|
||||
**Last Updated:** 2026-06-17
|
||||
|
||||
## Current Position
|
||||
|
||||
Milestone v0.2 shipped 2026-06-17. All 4 phases complete, 40/40 requirements satisfied.
|
||||
Next action: `/gsd:new-milestone` to define v0.3
|
||||
Phase: Not started (defining requirements)
|
||||
Plan: —
|
||||
Status: Defining requirements
|
||||
Last activity: 2026-06-17 — Milestone v0.3 started
|
||||
|
||||
## Phase Status
|
||||
|
||||
@@ -81,7 +82,7 @@ _Updated at each phase transition._
|
||||
|
||||
| Field | Value |
|
||||
|---|---|
|
||||
| Last session | 2026-06-17 — v0.2 milestone archived |
|
||||
| Next action | /gsd:new-milestone to define v0.3 |
|
||||
| Last session | 2026-06-17 — v0.3 milestone started |
|
||||
| Next action | Define v0.3 requirements and roadmap |
|
||||
| Pending decisions | None |
|
||||
| Resume file | None |
|
||||
|
||||
Reference in New Issue
Block a user