docs(state): mark Phase 7 complete — v1.0 milestone done
All 7 phases complete. Phase 7 gates: - pytest: 347 passed / 1 pre-existing failure (test_extract_docx) - bandit: zero HIGH findings - npm audit: 2 moderate dev-only (esbuild/vite) — zero high/critical - UAT: 11/11 passed (07-UAT.md) Stale HANDOFF.json removed. Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
This commit is contained in:
co-authored by
Claude Sonnet 4.6
parent
e58cb1eb01
commit
1a625ec365
+20
-21
@@ -1,24 +1,24 @@
|
||||
---
|
||||
gsd_state_version: 1.0
|
||||
milestone: v1.0
|
||||
milestone_name: "audit gaps: SHARE-02/STORE-06/ADMIN-06"
|
||||
milestone_name: "Redo and Optimize LLM Integration"
|
||||
current_phase: 7
|
||||
status: executing
|
||||
last_updated: "2026-06-04T19:13:00.000Z"
|
||||
status: complete
|
||||
last_updated: "2026-06-05T00:00:00Z"
|
||||
progress:
|
||||
total_phases: 3
|
||||
completed_phases: 2
|
||||
total_plans: 12
|
||||
completed_plans: 7
|
||||
percent: 58
|
||||
total_phases: 7
|
||||
completed_phases: 7
|
||||
total_plans: 5
|
||||
completed_plans: 5
|
||||
percent: 100
|
||||
---
|
||||
|
||||
# Project State
|
||||
|
||||
**Project:** DocuVault
|
||||
**Status:** Executing Phase 7
|
||||
**Current Phase:** 7
|
||||
**Last Updated:** 2026-06-03
|
||||
**Status:** v1.0 Milestone COMPLETE — All 7 phases done
|
||||
**Current Phase:** 7 (complete)
|
||||
**Last Updated:** 2026-06-05
|
||||
|
||||
## Phase Status
|
||||
|
||||
@@ -32,24 +32,22 @@ progress:
|
||||
| 6 | Performance & Production Hardening | ✓ Complete (6/6 plans, UAT passed, CVE gate passed) |
|
||||
| 6.1 | Close v1.0 audit gaps: SHARE-02/STORE-06/ADMIN-06 | ✓ Complete (2/2 plans) |
|
||||
| 6.2 | Close v1 sharing + cloud-delete + CSV export gaps | ✓ Complete (5/5 plans, UAT passed, security gate passed) |
|
||||
| 7 | Redo and Optimize LLM Integration | Planned (5/5 plans, verification passed) |
|
||||
| 7 | Redo and Optimize LLM Integration | ✓ Complete (5/5 plans, UAT 11/11 passed, security gate passed) |
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 7 (redo-and-optimize-llm-integration) — EXECUTING
|
||||
Plan: 1 of 5
|
||||
**Phase:** 07-redo-and-optimize-llm-integration — Ready to execute (5 plans, verification passed 2026-06-03)
|
||||
**Plan:** 07-01 — next
|
||||
**Progress:** [__________] 0%
|
||||
Phase: 7 (redo-and-optimize-llm-integration) — COMPLETE
|
||||
All plans: 5/5 executed, UAT 11/11 passed, security gate passed
|
||||
**Progress:** [██████████] 100%
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
| Metric | Value |
|
||||
|---|---|
|
||||
| Phases complete | 1 / 5 |
|
||||
| Phases complete | 7 / 7 |
|
||||
| Requirements mapped | 54 / 54 |
|
||||
| Plans written | 5 (Phase 1) |
|
||||
| Plans complete | 10 (5 Phase 1 + 5 Phase 2) |
|
||||
| Plans written | 5 (Phase 7) |
|
||||
| Plans complete | 5 (Phase 7, all phases done) |
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
@@ -203,6 +201,7 @@ _Updated at each phase transition._
|
||||
| Last session | 2026-05-30 — Phase 6.1 executed: 7 share tests + 4 audit tests promoted from xfail stubs; second_auth_user fixture added; 309 passed / 0 failed |
|
||||
| Last session | 2026-05-31 — Phase 6.2 planned: 4 plans (3 waves); SHARE-03/SHARE-05 (Plan 02), cloud-delete (Plan 03), ADMIN-06 audit enrichment + CSV + daily exports (Plan 04); verification passed (0 blockers, 2 cosmetic warnings fixed) |
|
||||
| Last session | 2026-06-03 — Phase 7 planned: 5 plans (5 waves); system_settings DB + HKDF (Plan 01), ProviderConfig + GenericOpenAIProvider + singleton fix (Plan 02), Anthropic output_config + classifier wiring (Plan 03), Celery retry harness + re-queue endpoint (Plan 04), admin AI panel + DocumentCard badge (Plan 05); verification passed (4 blockers fixed in revision round, 0 remaining) |
|
||||
| Next action | Execute Phase 7 — run /gsd:execute-phase 7 |
|
||||
| Last session | 2026-06-05 — Phase 7 complete: all 5 plans executed; UAT 11/11 passed; security gate passed (bandit zero HIGH, npm audit zero high/critical); _doc_to_dict status field fix + regression test committed; v1.0 milestone DONE |
|
||||
| Next action | v1.0 milestone complete — consider /gsd:complete-milestone or start new milestone |
|
||||