docs(08): create phase 8 plan — 8 plans, 3 waves (stack upgrade + backend decomposition)

Wave 0: CR-01/02/03 test stubs + api/schemas.py (CloudConnectionOut migration)
Wave 1: useToastStore stub + Phase 7.1 frontend completion
Wave 2 (parallel): api/admin/, api/documents/, api/auth/ package splits + client.js decomposition + PERF-01 deps

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
This commit is contained in:
curo1305
2026-06-08 14:59:27 +02:00
co-authored by Claude Sonnet 4.6
parent c20a5d8913
commit 25e568973f
12 changed files with 3109 additions and 16 deletions
+15 -15
View File
@@ -2,14 +2,14 @@
gsd_state_version: 1.0
milestone: v0.2
milestone_name: Phases
current_phase: Phase 8 (context gathered)
status: planning
last_updated: "2026-06-07"
last_activity: 2026-06-07 — Phase 8 context gathered
current_phase: "Phase 8: Stack Upgrade & Backend Decomposition"
status: planned
last_updated: "2026-06-08T00:00:00.000Z"
last_activity: 2026-06-08 — Phase 8 planned (8 plans, 3 waves)
progress:
total_phases: 17
completed_phases: 13
total_plans: 65
total_plans: 73
completed_plans: 65
percent: 76
---
@@ -17,22 +17,22 @@ progress:
# Project State
**Project:** DocuVault
**Status:** Phase 8 context gathered — ready to plan
**Status:** Phase 8 planned — ready to execute
**Current Phase:** Phase 8: Stack Upgrade & Backend Decomposition
**Last Updated:** 2026-06-07
**Last Updated:** 2026-06-08
## Current Position
Phase: Phase 8 (context gathered, not started)
Phase: Phase 8 (planned, 8 plans ready)
Plan: —
Status: Context captured — 8 areas discussed, 17 decisions locked
Last activity: 2026-06-07 — Phase 8 context gathered
Status: Ready to execute — 8 plans across 3 waves
Last activity: 2026-06-08 — Phase 8 planned
## Phase Status
| Phase | Requirements | Status |
|-------|-------------|--------|
| 8. Stack Upgrade & Backend Decomposition | PERF-01, CODE-01, CODE-02, CODE-03, CODE-04, CODE-08 | Not started |
| 8. Stack Upgrade & Backend Decomposition | PERF-01, CODE-01, CODE-02, CODE-03, CODE-04, CODE-08 | Planned (8 plans) |
| 9. Admin Panel Rearchitecture | ADMIN-08..12, CODE-06, CODE-09 | Not started |
| 10. UX & Interaction | UX-01..14, CODE-05 | Not started |
| 11. Visual Design, Responsive Layout & Cleanup | VISUAL-01..04, RESP-01..05, CODE-07, PERF-02, PERF-03 | Not started |
@@ -43,7 +43,7 @@ Last activity: 2026-06-07 — Phase 8 context gathered
|---|---|
| Phases complete | 0 / 4 |
| Requirements mapped | 40 / 40 |
| Plans written | 0 |
| Plans written | 8 |
| Plans complete | 0 |
## Accumulated Context
@@ -82,7 +82,7 @@ _Updated at each phase transition._
| Field | Value |
|---|---|
| Last session | 2026-06-07v0.2 roadmap created; 4 phases defined |
| Next action | /gsd:plan-phase 8 |
| Last session | 2026-06-08Phase 8 planned; 8 plans created |
| Next action | /gsd:execute-phase 8 |
| Pending decisions | None |
| Resume file | .planning/ROADMAP.md — Phase 8 detail section |
| Resume file | .planning/phases/08-stack-upgrade-backend-decomposition/ |