docs(phase-7): update tracking after wave 1 — plan 07-01 complete

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
This commit is contained in:
curo1305
2026-06-04 18:53:25 +02:00
co-authored by Claude Sonnet 4.6
parent 88f9175f28
commit 651713fa7a
2 changed files with 11 additions and 11 deletions
+2 -2
View File
@@ -402,7 +402,7 @@ Before any phase is marked complete, all three gates must pass:
**Wave 1** — Foundation: migration, ORM model, encryption helpers, Wave 0 test stubs **Wave 1** — Foundation: migration, ORM model, encryption helpers, Wave 0 test stubs
- [ ] 07-01-PLAN.md — Alembic migration 0005 (system_settings table) + SystemSettings ORM model + services/ai_config.py (HKDF helpers + load_provider_config + env seed on startup) + Wave 0 xfail stubs for D-01..D-16 (test_ai_providers.py, test_ai_config.py, test_admin_ai_config.py, test_document_tasks.py) - [x] 07-01-PLAN.md — Alembic migration 0005 (system_settings table) + SystemSettings ORM model + services/ai_config.py (HKDF helpers + load_provider_config + env seed on startup) + Wave 0 xfail stubs for D-01..D-16 (test_ai_providers.py, test_ai_config.py, test_admin_ai_config.py, test_document_tasks.py)
**Wave 2** *(blocked on Wave 1)* — Provider layer: ProviderConfig, GenericOpenAIProvider, singleton client fix, registry **Wave 2** *(blocked on Wave 1)* — Provider layer: ProviderConfig, GenericOpenAIProvider, singleton client fix, registry
@@ -456,4 +456,4 @@ Before any phase is marked complete, all three gates must pass:
| 6. Performance & Production Hardening | 3/6 | In Progress| | | 6. Performance & Production Hardening | 3/6 | In Progress| |
| 6.1. Close v1.0 audit gaps | 2/2 | Complete | 2026-05-30 | | 6.1. Close v1.0 audit gaps | 2/2 | Complete | 2026-05-30 |
| 6.2. Close v1 sharing + cloud-delete + CSV export gaps | 5/5 | Complete | 2026-05-31 | | 6.2. Close v1 sharing + cloud-delete + CSV export gaps | 5/5 | Complete | 2026-05-31 |
| 7. Redo and optimize LLM integration | 0/5 | Planned | | | 7. Redo and optimize LLM integration | 1/5 | In Progress| |
+9 -9
View File
@@ -4,19 +4,19 @@ milestone: v1.0
milestone_name: "audit gaps: SHARE-02/STORE-06/ADMIN-06" milestone_name: "audit gaps: SHARE-02/STORE-06/ADMIN-06"
current_phase: 7 current_phase: 7
status: executing status: executing
last_updated: "2026-06-03T16:24:52.248Z" last_updated: "2026-06-04T16:41:01.409Z"
progress: progress:
total_phases: 9 total_phases: 3
completed_phases: 7 completed_phases: 2
total_plans: 55 total_plans: 12
completed_plans: 44 completed_plans: 7
percent: 78 percent: 58
--- ---
# Project State # Project State
**Project:** DocuVault **Project:** DocuVault
**Status:** Phase 7 Planned — Ready to Execute **Status:** Executing Phase 7
**Current Phase:** 7 **Current Phase:** 7
**Last Updated:** 2026-06-03 **Last Updated:** 2026-06-03
@@ -36,8 +36,8 @@ progress:
## Current Position ## Current Position
Phase: 7 (redo-and-optimize-llm-integration) — PLANNED Phase: 7 (redo-and-optimize-llm-integration) — EXECUTING
Plan: 0 of 5 Plan: 1 of 5
**Phase:** 07-redo-and-optimize-llm-integration — Ready to execute (5 plans, verification passed 2026-06-03) **Phase:** 07-redo-and-optimize-llm-integration — Ready to execute (5 plans, verification passed 2026-06-03)
**Plan:** 07-01 — next **Plan:** 07-01 — next
**Progress:** [__________] 0% **Progress:** [__________] 0%