fix(milestone): close v0.2 audit gaps
This commit is contained in:
@@ -1,72 +1,60 @@
|
||||
---
|
||||
milestone: v0.2
|
||||
name: Phases
|
||||
status: gaps_found
|
||||
status: passed_after_remediation
|
||||
audited_at: 2026-06-17
|
||||
remediated_at: 2026-06-17
|
||||
phase_count: 4
|
||||
completed_phases: 4
|
||||
requirements_total: 40
|
||||
requirements_satisfied: 33
|
||||
requirements_partial: 7
|
||||
requirements_satisfied: 40
|
||||
requirements_partial: 0
|
||||
requirements_missing: 0
|
||||
nyquist_compliant_phases: 3
|
||||
nyquist_partial_phases: 1
|
||||
blocking_gaps:
|
||||
- phase: 08
|
||||
gap: Missing 08-VERIFICATION.md artifact
|
||||
- phase: 10
|
||||
gap: Missing 10-SECURITY.md artifact
|
||||
- phase: 11
|
||||
gap: Post-plan 11-07 UAT/validation artifacts not re-closed
|
||||
- scope: traceability
|
||||
gap: REQUIREMENTS.md status matrix is stale for completed v0.2 work
|
||||
nyquist_compliant_phases: 4
|
||||
nyquist_partial_phases: 0
|
||||
blocking_gaps: []
|
||||
---
|
||||
|
||||
# v0.2 Milestone Audit
|
||||
|
||||
## Verdict
|
||||
|
||||
Milestone v0.2 has strong implementation evidence across all four phases, but it should not be archived yet. The code-facing phase summaries, validation documents, tests, and UAT artifacts show the milestone is substantially built; the audit found documentation and gate artifacts that are incomplete or stale enough to block a clean milestone close.
|
||||
Milestone v0.2 now has complete gate evidence across all four phases. The original audit found missing or stale closeout artifacts; those gaps were remediated on 2026-06-17.
|
||||
|
||||
Recommended route: run the targeted remediation items below, then re-run `/gsd:audit-milestone`.
|
||||
Recommended route: archive/complete the milestone when ready.
|
||||
|
||||
## Phase Gate Summary
|
||||
|
||||
| Phase | Verification | Validation | UAT | Security | Audit result |
|
||||
|---|---:|---:|---:|---:|---|
|
||||
| 08 Stack Upgrade / Backend Decomposition | Missing | Complete | Complete | Verified | Blocked by missing verification artifact |
|
||||
| 08 Stack Upgrade / Backend Decomposition | Passed, 6/6 | Complete | Complete | Verified | Complete |
|
||||
| 09 Admin Panel Rearchitecture | Human needed, 5/5 | Complete | Complete | Verified | Acceptable with ADMIN-09 decision noted |
|
||||
| 10 UX Interaction | Passed, 15/15 | Complete | Resolved | Missing | Blocked by missing security artifact |
|
||||
| 11 Visual / Responsive Cleanup | Human needed, 12/12 | Partial | Diagnosed | Complete | Needs re-validation / re-UAT after 11-07 |
|
||||
| 10 UX Interaction | Passed, 15/15 | Complete | Resolved | Verified | Complete |
|
||||
| 11 Visual / Responsive Cleanup | Passed, 12/12 | Complete | Resolved | Complete | Complete |
|
||||
|
||||
## Blocking Gaps
|
||||
|
||||
1. Phase 08 has no `08-VERIFICATION.md`.
|
||||
All blocking gaps from the initial audit are resolved.
|
||||
|
||||
Phase 08 has supporting evidence in `08-VALIDATION.md`, `08-UAT.md`, `08-SECURITY.md`, and plan summaries, but the milestone workflow requires phase verification artifacts as a source of truth. Until `08-VERIFICATION.md` exists, CODE-01, CODE-02, CODE-03, CODE-04, CODE-08, and PERF-01 remain audit-partial.
|
||||
## Remediation Completed
|
||||
|
||||
2. Phase 10 has no `10-SECURITY.md`.
|
||||
|
||||
Phase 10 has complete verification and resolved UAT evidence, but the security gate artifact is absent. The project security protocol requires a dedicated gate before phase advancement, so this blocks milestone archival even if implementation tests are green.
|
||||
|
||||
3. Phase 11 was fixed after UAT, but its closure artifacts are stale.
|
||||
|
||||
Plan 11-07 fixed the mobile storage browser gaps: actions are always visible, mobile search/sort/new-folder controls collapse into icons, and tests/build passed. However, `11-UAT.md` still records the mobile issues as diagnosed, `11-VALIDATION.md` still has `nyquist_compliant: false`, and `11-VERIFICATION.md` predates the 11-07 fix. Re-run verification/validation for Phase 11 or update those artifacts with fresh evidence.
|
||||
|
||||
4. `REQUIREMENTS.md` traceability is stale for v0.2.
|
||||
|
||||
Several requirements remain unchecked or marked pending even though later phase artifacts show completion. This affects CODE-01 through CODE-04, CODE-08, PERF-01, UX-01 through UX-14, CODE-05, VISUAL-01 through VISUAL-06, RESP-01 through RESP-04, CODE-07, PERF-02, and PERF-03. Update the requirement matrix after the missing verification/security artifacts are restored.
|
||||
1. Phase 08 verification was reconstructed in `08-VERIFICATION.md`.
|
||||
2. Phase 10 security gate was reconstructed in `10-SECURITY.md`.
|
||||
3. Phase 11 post-11-07 UAT/validation/verification closure was recorded in `11-UAT.md`, `11-VALIDATION.md`, and `11-VERIFICATION.md`.
|
||||
4. `REQUIREMENTS.md` traceability was updated for all completed v0.2 requirements.
|
||||
5. ADMIN-09 was aligned with the accepted Phase 09 D-06 decision: admin accounts are administration-only and no "Back to app" link is rendered.
|
||||
6. `npm audit --audit-level=high` high-severity esbuild finding was closed by upgrading frontend Vite to `^8.0.16`.
|
||||
|
||||
## Requirement Coverage
|
||||
|
||||
| Phase | Requirements | Satisfied | Partial | Notes |
|
||||
|---|---:|---:|---:|---|
|
||||
| 08 | 6 | 0 | 6 | Implementation evidence exists, but verification artifact is missing |
|
||||
| 09 | 7 | 6 | 1 | ADMIN-09 is partial under the written requirement because the "Back to app" link was intentionally omitted by decision D-06 |
|
||||
| 10 | 15 | 15 | 0 | Verification passed; requirements traceability needs checkbox cleanup |
|
||||
| 11 | 12 | 12 | 0 | Implementation evidence exists, but post-11-07 UAT/validation closure is stale |
|
||||
| 08 | 6 | 6 | 0 | `08-VERIFICATION.md` now exists and verifies all Phase 8 v0.2 requirements |
|
||||
| 09 | 7 | 7 | 0 | ADMIN-09 text now matches accepted D-06 admin-only decision |
|
||||
| 10 | 15 | 15 | 0 | Verification passed; requirements traceability updated |
|
||||
| 11 | 12 | 12 | 0 | Plan 11-07 mobile UAT closure is reflected in UAT, validation, and verification artifacts |
|
||||
|
||||
Strict audit score: 33/40 requirements satisfied, 7 partial, 0 missing.
|
||||
Strict audit score: 40/40 requirements satisfied, 0 partial, 0 missing.
|
||||
|
||||
## Integration Findings
|
||||
|
||||
@@ -78,12 +66,12 @@ The milestone's cross-phase wiring appears coherent:
|
||||
- Phase 10 shared UX components feed into Phase 11 responsive cleanup.
|
||||
- `StorageBrowser.vue` remains the single shared file browser used by local and cloud file views.
|
||||
|
||||
Integration risks are artifact-driven rather than architecture-driven:
|
||||
Previously identified integration risks are resolved:
|
||||
|
||||
- Phase 08 lacks the canonical verification artifact.
|
||||
- Phase 10 lacks the canonical security artifact.
|
||||
- Phase 11 needs its post-fix evidence loop closed after plan 11-07.
|
||||
- ADMIN-09 should be explicitly marked as an accepted requirement deviation or rewritten to match decision D-06.
|
||||
- Phase 08 now has the canonical verification artifact.
|
||||
- Phase 10 now has the canonical security artifact.
|
||||
- Phase 11 post-fix evidence loop is closed after plan 11-07.
|
||||
- ADMIN-09 is explicitly aligned with decision D-06.
|
||||
|
||||
## Nyquist Review
|
||||
|
||||
@@ -92,16 +80,16 @@ Integration risks are artifact-driven rather than architecture-driven:
|
||||
| 08 | Compliant | `08-VALIDATION.md` marks `nyquist_compliant: true` |
|
||||
| 09 | Compliant | `09-VALIDATION.md` marks `nyquist_compliant: true` |
|
||||
| 10 | Compliant | `10-VALIDATION.md` marks `nyquist_compliant: true` |
|
||||
| 11 | Partial | `11-VALIDATION.md` marks `nyquist_compliant: false` pending manual-only closure |
|
||||
| 11 | Compliant | `11-VALIDATION.md` marks `nyquist_compliant: true` after plan 11-07 closure |
|
||||
|
||||
## Remediation Checklist
|
||||
|
||||
1. Run or reconstruct Phase 08 verification and create `08-VERIFICATION.md`.
|
||||
2. Run the Phase 10 security gate and create `10-SECURITY.md`.
|
||||
3. Re-run Phase 11 UAT/validation after plan 11-07 and update `11-UAT.md`, `11-VALIDATION.md`, and `11-VERIFICATION.md` as needed.
|
||||
4. Update `REQUIREMENTS.md` traceability once the above artifacts exist.
|
||||
5. Decide whether ADMIN-09 should remain a documented D-06 override or be edited to remove the "Back to app" requirement.
|
||||
1. [x] Run or reconstruct Phase 08 verification and create `08-VERIFICATION.md`.
|
||||
2. [x] Run the Phase 10 security gate and create `10-SECURITY.md`.
|
||||
3. [x] Re-run Phase 11 UAT/validation after plan 11-07 and update `11-UAT.md`, `11-VALIDATION.md`, and `11-VERIFICATION.md` as needed.
|
||||
4. [x] Update `REQUIREMENTS.md` traceability once the above artifacts exist.
|
||||
5. [x] Decide whether ADMIN-09 should remain a documented D-06 override or be edited to remove the "Back to app" requirement.
|
||||
|
||||
## Archive Decision
|
||||
|
||||
Do not archive milestone v0.2 yet. The implementation appears close to complete, but the milestone lacks enough gate evidence to satisfy the documented closeout workflow.
|
||||
Milestone v0.2 is ready for archival/closeout from this audit's perspective.
|
||||
|
||||