gsd_state_version: 1.0
|
||
milestone: v0.2
|
||
milestone_name: "UI Overhaul and Optimization"
|
||
current_phase: none
|
||
status: planning
|
||
last_updated: "2026-06-07T00:00:00.000Z"
|
||
progress:
|
||
total_phases: 4
|
||
completed_phases: 0
|
||
total_plans: 0
|
||
completed_plans: 0
|
||
percent: 0
|
||
---
|
||
|
||
# Project State
|
||
|
||
**Project:** DocuVault
|
||
**Status:** Milestone v0.2 roadmap defined — ready to plan Phase 8
|
||
**Current Phase:** None (roadmap approved, planning begins)
|
||
**Last Updated:** 2026-06-07
|
||
|
||
## Current Position
|
||
|
||
Phase: Not started
|
||
Plan: —
|
||
Status: Roadmap created — 4 phases defined, 40 requirements mapped
|
||
Last activity: 2026-06-07 — v0.2 roadmap created
|
||
|
||
## Phase Status
|
||
|
||
| Phase | Requirements | Status |
|
||
|-------|-------------|--------|
|
||
| 8. Stack Upgrade & Backend Decomposition | PERF-01, CODE-01, CODE-02, CODE-03, CODE-04, CODE-08 | Not started |
|
||
| 9. Admin Panel Rearchitecture | ADMIN-08..12, CODE-06, CODE-09 | Not started |
|
||
| 10. UX & Interaction | UX-01..14, CODE-05 | Not started |
|
||
| 11. Visual Design, Responsive Layout & Cleanup | VISUAL-01..04, RESP-01..05, CODE-07, PERF-02, PERF-03 | Not started |
|
||
|
||
## Performance Metrics
|
||
|
||
| Metric | Value |
|
||
|---|---|
|
||
| Phases complete | 0 / 4 |
|
||
| Requirements mapped | 40 / 40 |
|
||
| Plans written | 0 |
|
||
| Plans complete | 0 |
|
||
|
||
## Accumulated Context
|
||
|
||
### Key Decisions
|
||
|
||
*(Carries forward from v0.1 — see PROJECT.md for full decision log.)*
|
||
|
||
| Decision | Rationale |
|
||
|---|---|
|
||
| Options API preserved in v0.2 refactor | Composition API migration is scope-creep; refactor within Options API |
|
||
| Admin panel as standalone route subtree | AdminView as tabs-on-user-layout is architecturally wrong; v0.2 fixes this |
|
||
| No rewrites — refactor only | Preserve existing tests and behavior; change internal structure, not contracts |
|
||
| client.js barrel re-export pattern | Zero consumer churn; all 35+ import sites stay unchanged; mocks still work |
|
||
| Sub-routers carry NO prefix | Parent APIRouter prefix propagates — sub-routers with prefix cause double-segment URLs |
|
||
| AdminLayout as route component, not App.vue branch | Router resolves AdminLayout as the /admin component; its router-view renders children |
|
||
| to.matched.some() for requiresAdmin guard | Vue Router 4 does not inherit meta to children; direct to.meta check is a security regression |
|
||
|
||
### Roadmap Evolution
|
||
|
||
- v0.1 completed: all 7 foundation phases + security hardening (2026-06-06)
|
||
- v0.2 started: UI overhaul, code quality, admin panel rearchitecture (2026-06-07)
|
||
- v0.2 roadmap defined: 4 phases, 40 requirements, phases 8–11 (2026-06-07)
|
||
|
||
### Open Questions
|
||
|
||
None.
|
||
|
||
### Blockers
|
||
|
||
None.
|
||
|
||
## Session Continuity
|
||
|
||
_Updated at each phase transition._
|
||
|
||
| Field | Value |
|
||
|---|---|
|
||
| Last session | 2026-06-07 — v0.2 roadmap created; 4 phases defined |
|
||
| Next action | /gsd:plan-phase 8 |
|
||
| Pending decisions | None |
|
||
| Resume file | .planning/ROADMAP.md — Phase 8 detail section |
|