gsd_state_version: 1.0
|
||
milestone: v0.2
|
||
milestone_name: Phases
|
||
current_phase: 9
|
||
status: executing
|
||
last_updated: "2026-06-12T13:43:18.883Z"
|
||
last_activity: 2026-06-12 -- Phase 9 execution started
|
||
progress:
|
||
total_phases: 4
|
||
completed_phases: 1
|
||
total_plans: 13
|
||
completed_plans: 8
|
||
percent: 25
|
||
---
|
||
|
||
# Project State
|
||
|
||
**Project:** DocuVault
|
||
**Status:** Executing Phase 9
|
||
**Current Phase:** 9
|
||
**Last Updated:** 2026-06-12
|
||
|
||
## Current Position
|
||
|
||
Phase: 9 (Admin Panel Rearchitecture) — EXECUTING
|
||
Plan: 1 of 5
|
||
Status: Executing Phase 9
|
||
Last activity: 2026-06-12 -- Phase 9 execution started
|
||
|
||
## Phase Status
|
||
|
||
| Phase | Requirements | Status |
|
||
|-------|-------------|--------|
|
||
| 8. Stack Upgrade & Backend Decomposition | PERF-01, CODE-01, CODE-02, CODE-03, CODE-04, CODE-08 | **Complete (8/8 plans)** |
|
||
| 9. Admin Panel Rearchitecture | ADMIN-08..12, CODE-06, CODE-09 | Not started |
|
||
| 10. UX & Interaction | UX-01..14, CODE-05 | Not started |
|
||
| 11. Visual Design, Responsive Layout & Cleanup | VISUAL-01..04, RESP-01..05, CODE-07, PERF-02, PERF-03 | Not started |
|
||
|
||
## Performance Metrics
|
||
|
||
| Metric | Value |
|
||
|---|---|
|
||
| Phases complete | 1 / 4 |
|
||
| Requirements mapped | 40 / 40 |
|
||
| Plans written | 8 |
|
||
| Plans complete | 8 |
|
||
|
||
## Accumulated Context
|
||
|
||
### Key Decisions
|
||
|
||
*(Carries forward from v0.1 — see PROJECT.md for full decision log.)*
|
||
|
||
| Decision | Rationale |
|
||
|---|---|
|
||
| Options API preserved in v0.2 refactor | Composition API migration is scope-creep; refactor within Options API |
|
||
| Admin panel as standalone route subtree | AdminView as tabs-on-user-layout is architecturally wrong; v0.2 fixes this |
|
||
| No rewrites — refactor only | Preserve existing tests and behavior; change internal structure, not contracts |
|
||
| client.js barrel re-export pattern | Zero consumer churn; all 35+ import sites stay unchanged; mocks still work |
|
||
| Sub-routers carry NO prefix | Parent APIRouter prefix propagates — sub-routers with prefix cause double-segment URLs |
|
||
| AdminLayout as route component, not App.vue branch | Router resolves AdminLayout as the /admin component; its router-view renders children |
|
||
| to.matched.some() for requiresAdmin guard | Vue Router 4 does not inherit meta to children; direct to.meta check is a security regression |
|
||
| FastAPI 0.128+ empty-path sub-router restriction | `@router.get("")` on sub-router with empty include prefix fails; register root routes on parent aggregator |
|
||
| Vite 6 upgrade resolves 2 CVEs | CVE-2026-39363/39364 closed; npm audit now clean |
|
||
|
||
### Roadmap Evolution
|
||
|
||
- v0.1 completed: all 7 foundation phases + security hardening (2026-06-06)
|
||
- v0.2 started: UI overhaul, code quality, admin panel rearchitecture (2026-06-07)
|
||
- v0.2 roadmap defined: 4 phases, 40 requirements, phases 8–11 (2026-06-07)
|
||
|
||
### Open Questions
|
||
|
||
None.
|
||
|
||
### Blockers
|
||
|
||
None.
|
||
|
||
## Session Continuity
|
||
|
||
_Updated at each phase transition._
|
||
|
||
| Field | Value |
|
||
|---|---|
|
||
| Last session | 2026-06-12 — Phase 8 complete; all 8 plans executed |
|
||
| Next action | /gsd:discuss-phase 9 then /gsd:plan-phase 9 |
|
||
| Pending decisions | None |
|
||
| Resume file | .planning/phases/ (phase 9 not yet created) |
|